Phase 1 of the Roadway Redevelopment Project will take place along the frontage of the Indian Creek Country Club; between Lots 14 and 15. This work will include the excavation of the entire existing roadway, the replacement of the drainage system, the installation of sewer utility lines and the rebuilding of a roadway bed with a drivable surface. Each phase of the project will include the same scope of work. The final stage of the project will be the landscaping, pathway trail, street lighting and application of the last top layer of the road.
Phase 1 will be completed by October 1, 2021.
June-29-2021-duration-35-days